Berlin, May 06, 2002 – The EMBRAER170 flight test campaign, which is proceeding on schedule, will see additional prototype and test article aircraft join the program by June 2002.

A total of six airplanes will be involved in the flight test campaign, which started with the February 19th, 2002, maiden flight of prototype S/N 0001. Prototype S/N 0002 took to the skies on April 9th and, to date, the program has accumulated a total of 101 hours & 20 minutes, from 60 flights.

The other EMBRAER 170 prototypes are scheduled to fly by mid-May (S/N 0003), the beginning of June (S/N 0004), in mid June (S/N 0005) and at the end of June (S/N 0006). These aircraft are currently in the final assembly stages at Embraer’s São José dos Campos production facility located 80 km northeast of São Paulo, Brazil. Final assembly is being performed at Hangar F-220, a facility specially designed and built to support the new “assembly docks” production philosophy, which has been adopted by the Company for its EMBRAER 170/190 aircraft family.

Prototypes S/N 0001 and 0002 will be used primarily to explore and validate the flight envelope, as well as aircraft stability and handling qualities. Ground vibration tests for flutter analysis and natural stalls have already been performed with both aircraft.

Prototypes S/N 0003 and 0004 will be used primarily for systems and avionics testing. They will be equipped with the latest version of the Honeywell EPIC avionics suite.

Prototypes S/N 0005 and 0006 will be the only prototypes fitted with a complete interior. They will be used for systems development, function and reliability testing, route-proving and final certification. Both prototypes will be tasked with interior validation, baggage compartment certification and internal/external noise testing as well as environmental noise and emissions testing.

Total flight-test time with the six prototypes is expected to be approximately 1,800 flight hours.

The EMBRAER 170 certification program also includes ground testing to be conducted with two complete airframes for both the static and fatigue tests at Embraer’s São José dos Campos facility.

Together with this extensive fleet of pre-series aircraft and airframes, Embraer is using a so-called “Iron Bird” to further reduce the time-to-certification of the EMBRAER 170. This device is a test rig of the hydraulic system, complete flight controls (fly-by-wire) with counter-actuators simulating the aerodynamic loading through the entire aircraft flight envelope, landing gear, engine thrust reverser, and main avionics equipment. It is used for development, troubleshooting, verification and validation of the systems for certification.

“The EMBRAER 170 represents the very best in terms of technology, comfort, efficiency and performance”, explains Luiís C. Affonso, EMBRAER 170/190 Program Director. “Thanks to its new design, and the state-of-the-art technical solutions that have been selected for it, the EMBRAER 170 represents, by far, the best product in its category and we anticipate many more customers to share that point of view in the future.”

Successful completion of the flight test program is expected to lead to the certification of the EMBRAER 170 in the first quarter of 2003, prior to delivery to launch customer SWISS of Switzerland.

The development of the other aircraft family members, the EMBRAER 175, 195 and 190, is progressing as planned, with first deliveries scheduled for July 2004, December 2004 and December 2005, respectively.